VARIOKIT Cantilevered Parapet Systems in action
-
The parapet track is suspended from the underside of the bridge by means of rails and roller units ensuring the working area and formed parapet are always easily accessible
-
With the parapet track, multiple 20 m long centre and outer parapet sections can be shuttered, concreted and struck per week – ensuring unrestricted use of the carriageway.
-
The parapet carriage moving on the bridge superstructure can easily be adapted to accommodate obstructions and any changes in the cross-section. All necessary adjustment work is carried out from the working platform.
-
Moving the parapet carriage takes place quickly and easily by means of steel profiles. As a rule, no anchoring is required in the structure and horizontal forces are transferred via friction.
##product.details.headline##
Interested in using VARIOTKIT for your next project?
Please contact us via phone: 1234567