A 153 m heighted 46 storey tower
finished in year 2013.
A customised system which takes care of pace construction as well as safety of workmen working on the height of 300 ft. A system which makes it easier to construct higher easier and fisible.
Shapoorji Pallonji
Using PERI formwork systems ensure to achieve core cycle time in 6 days which has helped us to complete slab in 8 days cycle. Also from safety point of view, it is helpful to work at any height.”
This project utilizes ACS P climbing system with VARIO GT 24 wall formwork. VARIO GT 24 wall formwork of 365 m² has been supplied which is supported on ACS P with Gallows system. There are 2 ACS P units which cover whole core area of 365 m² and outer panels are supported through gallows system.